Reconstruction of Munalaskme central voltage substation (M6-M74) (IP7868) in Harju County, Saue Municipality, villages of Aude, Munalaskme and Kibuna

Closed

Submission Deadline Has Passed

This tender's submission deadline has passed and is no longer accepting applications. The information below is kept for reference purposes.

Browse Active Tenders
Deadline
Expired
March 09, 2026
Contract Details
Category
Construction
Reference
306264
Value
€175,000
Location
Estonia
Published
February 26, 2026
Organization
CPV Code
Evaluation Criteria
Total bid cost100%
Project Timeline

Tender Published

February 26, 2026

Deadline for Questions

March 02, 2026

Submission Deadline

March 09, 2026

Tender Opening

March 09, 2026

Contract Start Date

March 17, 2026

Win ProbabilityPRO
🔒
Upgrade to Professional
See your estimated win probability based on historical data.
Upgrade to Professional →
Buyer IntelligencePRO
🔒
Unlock Buyer Intelligence
See spending patterns, preferred procedures, and more.
Upgrade to Professional →
Sector InsightsPRO
🔒
Unlock Sector Insights
See average winning prices, competition levels, and market trends.
Upgrade to Professional →
Budget
€175,000
Duration
Not specified
Location
Estonia
Type
Construction
75
Quality Score/100
Good
Market Benchmark
Avg. Winning Price
€524,963
Avg. Bids
4.7
Competition
Medium
SME Winners
94%
5,932 tenders analyzed

Original Tender Description

The tender is announced for the reconstruction of the Munalaskme central voltage substation (M6-M74) (IP7868) located in the villages of Aude, Munalaskme and Kibuna, Saue Municipality, Harju County. Construction according to the project and additional conditions. The deadline for completion of works is 17.07.2026. - Overhead power line 62 mm2 (BLL62) to be supplied by the contracting authority. Handover in March 2026. Transport of equipment and materials to be procured by the contracting authority and associated costs from the supplier to the site are included in the scope of the tenderer's work. If possible and necessary, the contract may be concluded and the execution of works/ordering of services may commence before the estimated start date of the contract validity published in the general information about the tender. If the tender procedure takes longer, the contract may be concluded and its execution may commence even after the estimated start date of the contract validity published in the general information. The deadline for the execution of works will not change.
EU FundedElectronic Submission

Run Risk Analysis

Identify potential risks, inconsistencies, and red flags across all tender documents. Get a detailed risk report with severity levels and mitigation recommendations.

Login

Win Strategy

AI-powered analysis of this tender's requirements, opportunities, and challenges. Get strategic insights to maximize your win probability.

70%
Estimated Win ProbabilityModerate Fit

This tender for the reconstruction of the Munalaskme central voltage divider presents a moderate competition opportunity. Success hinges on demonstrating strong technical capability in similar electrical construction, meticulous project planning, and a cost-effective, compliant bid. While social value and innovation are not explicitly weighted, proactive inclusion can serve as a differentiator.

Key Winning Messages

Reliable and Experienced Electrical Infrastructure Reconstruction

Efficient Project Delivery within Strict Timelines

Cost-Effective and Compliant Solution

Key Opportunities
Early engagement with the project and site familiarization can lead to a more accurate and competitive bid.
The tender allows for contract commencement before the official start date, offering flexibility for early project initiation.
While not explicitly weighted, demonstrating proactive social value commitments can differentiate the bid.
Key Challenges
Lack of specified evaluation criteria means bidders must assume a strong emphasis on technical compliance and price.

Focus on a technically sound proposal that meticulously addresses all project requirements and a highly competitive pricing strategy. Ensure all mandatory and eligibility criteria are met without any ambiguity.

The tender documents are in Estonian and require careful translation and understanding of local nuances.

Engage professional translation services and, if possible, local consultants or team members to ensure accurate interpretation of all technical and contractual terms.

The estimated value is relatively low, suggesting potential for multiple bidders with competitive pricing.

Develop a lean and efficient project plan to minimize costs without compromising quality or safety. Leverage existing resources and supply chains to achieve cost efficiencies.

Ideal Bidder Profile
An experienced electrical construction company with a proven track record in overhead line reconstruction, possessing the necessary electrical supervisor and switching rights personnel. They must be adept at detailed cost estimation and project scheduling, capable of delivering within the specified timeframe and adhering to all technical specifications.
Key Requirements
Possession of a valid A-competence electrical work supervisor.
Possession of an employee with switching rights.
Successfully completed similar electrical construction works contracts within the last 60 months, with at least one contract valued at €40,000 or more.
Familiarization with the site and project before submitting a bid.
Submission of a completed cost table.
Submission of a work execution schedule.
Bidder must prove they do not have mandatory exclusion grounds.
Key Discriminators
Demonstrated proactive approach to site familiarization and project understanding.
Clear and concise work execution schedule that optimizes efficiency and timeline adherence.
Proactive, albeit not mandatory, inclusion of social value commitments (e.g., local employment, waste reduction).
Exceptional clarity and completeness in the cost table, demonstrating thoroughness and accuracy.
Social Value Opportunities
Commitment to minimizing environmental impact during construction, such as responsible waste management and dust control.
Preference for local suppliers and subcontractors where feasible to support the local economy.
Bid Focus Areas
Technical Compliance

Ensure every aspect of the project description and technical specifications is addressed. Highlight the qualifications of personnel and past project successes that directly align with the tender's technical demands.

Price

Develop a detailed cost breakdown that is competitive yet profitable. Ensure all costs are accounted for, including those related to the transport of materials provided by the buyer.

Experience and Capability

Thoroughly document past similar projects, emphasizing scale, complexity, and successful outcomes. Clearly present the CVs and certifications of the key personnel, especially the electrical supervisor and switching rights holder.

Recommendations7
Verify and Document Personnel Qualifications
CriticalLow effort

Ensure the bid explicitly confirms the possession of a valid A-competence electrical work supervisor and an employee with switching rights. Provide copies of certifications or relevant documentation as required.

Ensures compliance with mandatory eligibility criteria, preventing immediate disqualification.
Thorough Site and Project Familiarization
CriticalMed effort

Conduct a detailed site visit and in-depth review of the project documentation (Projekt_IP7868, Lisatingimused_IP7868). Document this process and use the insights to inform the work execution schedule and costings, demonstrating a proactive understanding.

Leads to a more accurate and competitive bid, and demonstrates commitment to the project.
Proactive Social Value Integration
HighMed effort

Although not explicitly required, include a section detailing commitments to local employment, waste reduction, or environmental best practices during the project execution. Frame this as a commitment to responsible project delivery.

Can differentiate the bid from competitors who do not address social value, potentially influencing the decision-maker.
Meticulous Cost Table Completion
CriticalHigh effort

Complete the cost table with utmost accuracy and detail. Ensure all costs, including those for transporting buyer-provided materials, are clearly itemized and justified. Cross-reference with the project scope and schedule.

Directly impacts the financial evaluation and demonstrates bid completeness and professionalism.
Translate and Understand All Tender Documents
HighMed effort

Utilize professional translation services for all Estonian-language documents. If possible, have a native speaker or local expert review the translated documents to ensure full comprehension of nuances and specific requirements.

Prevents misinterpretation of requirements, which could lead to non-compliant bids or contractual issues.
Develop a Robust Work Execution Schedule
HighHigh effort

Create a detailed and realistic work execution schedule that clearly outlines phases, milestones, and resource allocation. Ensure it aligns with the project deadline of 17.07.2026 and accounts for the delivery of buyer-provided materials in March 2026.

Demonstrates project management capability and a clear plan for successful and timely completion.
Document Past Similar Contracts
CriticalMed effort

Provide detailed information on at least three similar electrical construction works contracts completed in the last 60 months. Ensure one contract clearly exceeds the €40,000 threshold, providing evidence of value and experience.

Meets a critical eligibility and technical capability requirement.
Competitive Positioning
Position the bid as the most reliable and experienced choice for critical electrical infrastructure upgrades, emphasizing a proven track record in similar projects.
Highlight the efficiency and cost-effectiveness of the proposed solution, demonstrating a clear understanding of the project's value and the need for competitive pricing.
Showcase a proactive and professional approach through detailed planning and site familiarization, setting the bid apart from potentially less thorough competitors.

Competitors

Upgrade to see which companies are likely to bid on this tender, based on historical procurement data.

Login

Requirements & Qualifications

13 requirements across 5 categories

Submission (5)
Mandatory (1)
Compliance (5)
Technical (1)
Financial (1)
SUBMISSION REQUIREMENTS5
--Bidder must familiarize themselves with the site and project before submitting a bid.
--Bidder must submit a complete bid including all necessary materials and a work execution schedule.
--Bidder must submit information on at least three similar electrical construction works contracts from the last 60 months.
MANDATORY EXCLUSION GROUNDS1
--Bidder must prove they do not have mandatory exclusion grounds.
ELIGIBILITY REQUIREMENTS5
--Bidder must confirm their bid meets all conditions in the tender documents.
--Bidder must possess a valid A-competence electrical work supervisor.
--Bidder must possess an employee with switching rights.
TECHNICAL CAPABILITY REQUIREMENTS1
--Bidder must have completed similar electrical construction works contracts within the last 60 months.
FINANCIAL REQUIREMENTS1
--None explicitly stated beyond the value of previous contracts.

Requirements Preview

Sign up to view complete requirements and analysis

Documents

5 documents available with AI summaries

VastavustingimusedPDF
306264_vastavustingimused.pdf -- 9.9 KB

Bidders must confirm that their bid meets all conditions set forth in the tender documents, including possessing a qualified electrical work supervisor with valid A-competence and a switching-authorized employee, and submitting a completed cost table.

Varasemate hankelepingute informatsioonDOC
Varasemate hankelepingute informatsioon.docx -- 22.3 KB

Bidders must provide information on at least three similar electrical construction contracts completed in the last 60 months, with at least one contract valued at €40,000 or more.

Hindamiskriteeriumid ja hinnatavad näitajadPDF
306264_hindamiskriteeriumid.pdf -- 2.9 KB

The contracting authority will evaluate bids primarily based on the total cost, where the lowest price receives the maximum score.

Kõrvaldamise alused ja kvalifitseerimistingimusedPDF
306264_korvaldamise_alused_ja_kvalifitseerimi... -- 7.1 KB

The bidder must confirm the absence of mandatory exclusion grounds and meet qualification criteria, including having at least three similar electrical construction contracts successfully completed within the last 60 months.

Lisatingimused_IP7868DOC
Lisatingimused_IP7868.docx -- 17.1 KB

Before submitting a bid, the contractor must familiarize themselves with the site and project, and submit a complete bid including all necessary materials and a work execution schedule.

Documents Preview

Sign up to view document summaries and analysis

75
Good

Tender Quality Score

This tender for electrical infrastructure reconstruction is generally well-structured with clear requirements and a reasonable process. However, it lacks explicit sustainability considerations and has some minor practical limitations regarding document accessibility.

Score Breakdown

Legal Compliance75/100

The tender adheres to standard legal requirements for public procurement, including a clear procedure, proper CPV code, and reasonable deadlines. There are no immediate indications of disputes or regulatory non-compliance.

Clarity80/100

The description of the works is clear, and the requirements are documented. Evaluation criteria are mentioned as 'relative_weighting', implying a structured approach, though specific weighting is not detailed.

Completeness70/100

Most basic information is present, including deadlines, value, and duration. However, some crucial documents (Projekt_IP7868, Maksumuse_tabel_IP7868) are in formats not supported by AI analysis, potentially hindering full understanding without manual access.

Some essential tender documents are in unsupported file formats for AI analysis.
Fairness85/100

The tender promotes fairness through e-submission and e-procurement. Requirements for previous contracts are objective and not tailored to specific companies. Full document access is implied, though some formats are problematic.

Practicality65/100

E-submission is available, and a contract start date is specified. However, the financing condition details are complex, and the link to 'hankedokumendid' for factoring program details might require further navigation.

Financing conditions are detailed but require careful review, especially regarding factoring program participation.
Data Consistency90/100

Key fields are populated, and dates appear logical. There are no indications of suspension or disputes, contributing to high data consistency.

Sustainability50/100

The tender is EU funded, which is a positive aspect. However, there are no explicit mentions of green procurement, social aspects, or innovation, which are common in modern tenders.

Lack of explicit green procurement, social, or innovation criteria.

Strengths

Clear description of works and location.
E-submission and e-procurement enabled.
Objective evaluation criteria (implied by relative weighting).
EU funded project.

Concerns

Some critical documents are in unsupported file formats.
Absence of explicit sustainability criteria (green, social, innovation).
Complex payment terms requiring careful bidder review.

Recommendations

1. Ensure all tender documents are accessible in standard, AI-analyzable formats.
2. Consider incorporating specific sustainability objectives into future tenders.
3. Provide a more direct link or summary for the factoring program details.

AI Scoring Preview

Sign up to view complete requirements and analysis

Complete quality score analysis
Detailed sub-score breakdown
Strengths & concerns insights
Strategic recommendations

No credit card required • Setup in 2 minutes

New Service

Want us to handle this tender?

Our procurement experts prepare everything. Proven to work — you review, approve, and submit.

~1hYour time only
80%+80%+
$0Upfront
See full comparison
Without TaaSWith TaaS
40-80 hrs
Preparation time
~1 hr
Your time only
15-25%
Average win rate
80%+
Win rate
Risk of errors
Manual review
Expert QA
Compliance check
You do all
Handle everything
We do all
End-to-end service
Let's Win This Tender
Pay only when you win · 400+ companies trust us
Or do it yourself

Add to Pipeline