This mandatory Elektrilevi OÜ tender requires an A-licenced (or EQF-6) electrical works supervisor registered in EPP, proven 0.22–20 kV switching authority, strict compliance with the supplied project and standards, completion by 29 May 2026, and full pricing in the provided Excel template—bid only if you can supply all materials except Elektrilevi-provided equipment and accept 14- to 45-day payment terms.
Mandatory qualification: you must prove (via 3 reference contracts in the last 5 years, at least one ≥ €200k) that you can install medium-voltage grids, then deliver the Kiia/Vahi network upgrade (materials mostly supplied, completion by 29 May 2026) – if you lack these exact references, skip the bid.
This is a 100% price-only tender for Elektrilevi OÜ’s medium-voltage network upgrade in Kiia & Vahi villages (completion mandatory by 29.05.2026), where bidders must supply all materials except those listed by the client, execute per project/specs, and hold valid electrical-installation qualifications; bid only if you can deliver the full scope at the lowest tax-excluded price.
Elektrilevi OÜ’s €-type procurement for medium-voltage grid upgrades in Keila-Tutermaa (Harju county) requires the contractor to execute works by 29 May 2026 per supplied project and special terms—Elektrilevi supplies poles, transformers, KP cable, BLL99 and substations while the bidder supplies all other materials—subject to mandatory exclusion checks (no tax/sanction/corruption history) and compliance with applicable standards; bid only if your firm has proven 20 kV+ grid construction capacity, can self-perform by the fixed date and can certify clean criminal/tax status.
Mandatory site visit & quantity verification required before pricing: Elektrilevi will supply only arvestid/trafod/KP-cable/BLL99/substations, bidder must self-source all other materials, deliver full works—including undocumented auxiliaries—by 29.05.2026, provide geodetically-signed as-built drawings and pre/post-work photos, coordinate outages with priority clients, notify relay/automation team 30 days pre-energisation, and assume full liability for land-owner damages—making this suitable only for experienced MV-network contractors with strong project-management, surveying and stakeholder-coordination capabilities.
Inscrivez-vous pour consulter les résumés et l'analyse des documents
L'analyse de la qualité de cet appel d'offres est en cours. Veuillez vérifier à nouveau dans quelques instants.
Bonjour ! Je suis votre assistant IA pour cet appel d'offres. Je peux vous aider à comprendre les exigences, les délais, les critères d'admissibilité et vous fournir des informations stratégiques.
Aucune carte de crédit requise