Brug for hjælp fra en udbudsekspert? Se vores udbudsforberedelsestjeneste
Udbud

Construction of Pärna 110 kV substation

Lukket

Fristen for indsendelse er overskredet

Fristen for indsendelse af dette udbud er overskredet, og der modtages ikke længere ansøgninger. Oplysningerne nedenfor er gemt til referenceformål.

Gennemse aktive udbud
Frist
Udløbet
23. marts 2026
Kontrakt detaljer
Kategori
Byggeri
Reference
306637
Værdi
€2,700,000
Lokation
Estonia, Estland
Udgivet
2. marts 2026
Organisation
CPV-kode
Evalueringskriterier
Total bid price in euros excluding VAT100%
Projekttidslinje

Udbud offentliggjort

2. marts 2026

Frist for spørgsmål

16. marts 2026

Frist for tilbud

23. marts 2026

Åbning af udbud

23. marts 2026

VinderchancePRO
🔒
Opgrader til Professional
Se din estimerede vinderchance baseret på historiske data.
Opgrader til Professionel →
OrdregiverindsigtPRO
🔒
Lås op for ordregiverindsigt
Se forbrugsmønstre, foretrukne procedurer og mere.
Opgrader til Professionel →
SektorsindsigtPRO
🔒
Lås op for sektorsindsigt
Se gennemsnitlige vinderpriser, konkurrenceniveauer og markedstrends.
Opgrader til Professionel →
Budget
€2,700,000
Varighed
26 måneder
Lokation
Estonia
Type
Byggeri
75
Kvalitetsscore/100
God
Markedsbenchmark
Gns. Vindende Pris
€524,963
Gns. Tilbud
4.7
Konkurrence
Medium
SMV Vindere
94%
5,932 udbud analyseret

Original udbudsbeskrivelse

Elering AS is building the Pärna 110 kV substation. Technical documentation (Security project) is confidential. Technical documentation can be reviewed after signing a confidentiality agreement (attached in the "Documents" section). Please submit the signed confidentiality agreement via RHR communication. The contracting authority will return the confidentiality agreement signed by both parties and will make the confidential technical documents available to the bidder within three working days of receiving the bidder's signed confidentiality agreement.
Elektronisk Afsendelse

Kør risikoanalyse

Identificer potentielle risici, uoverensstemmelser og advarselstegn på tværs af alle udbudsdokumenter. Få en detaljeret risikorapport med alvorlighedsgrader og anbefalinger til afhjælpning.

Log ind

Vinderstrategi

AI-drevet analyse af dette udbuds krav, muligheder og udfordringer. Få strategiske indsigter for at maksimere din vinderchance.

65%
Estimeret vinderchanceModerat match

This tender for the Pärna 110 kV substation construction is heavily weighted on price (100%). A winning strategy will focus on meticulous cost management, demonstrating robust technical capability, and ensuring strict adherence to all mandatory requirements. Given the lack of explicit social value or innovation criteria, competitive differentiation will stem from price leadership and flawless execution.

Nøglebudskaber til at vinde

Unbeatable Price Leadership: Delivering the Pärna 110 kV substation at the most competitive price without compromising quality or compliance.

Technical Excellence & Proven Delivery: Demonstrating deep technical expertise in high-voltage substation construction and a history of successful project execution.

Seamless Compliance & Risk Mitigation: Ensuring absolute adherence to all tender requirements and proactively managing potential risks for a smooth project lifecycle.

Nøglemuligheder
Leveraging economies of scale and optimized supply chain for cost reduction.
Early engagement with Elering AS post-confidentiality agreement to clarify technical details and ensure alignment.
Proactive identification and pre-qualification of reliable subcontractors to ensure compliance and cost control.
Nøgleudfordringer
Intense price competition due to 100% price weighting.

Conduct thorough cost analysis, explore all avenues for cost optimization (e.g., bulk purchasing, efficient logistics), and ensure all indirect costs are accurately accounted for to avoid underbidding.

Confidentiality of technical documentation requiring a structured approach to review and bid preparation.

Immediately sign and submit the confidentiality agreement to gain access to technical documents. Allocate dedicated technical and procurement teams to review these documents promptly and thoroughly.

Ensuring all mandatory requirements, especially those related to exclusion grounds and subcontractor checks, are met flawlessly.

Implement a rigorous internal checklist and review process for all mandatory documentation. Engage legal counsel if necessary to ensure all exclusion ground confirmations are accurate and complete.

Ideel tilbudsgiverprofil
An experienced electrical infrastructure contractor with a proven track record in high-voltage substation construction, strong project management capabilities, a highly efficient supply chain, and a demonstrated ability to deliver projects within budget and on time. The ideal bidder will have a deep understanding of Estonian regulatory requirements and a strong financial standing to support the project's financing schedule.
Nøglekrav
Submission of completed questionnaires '031A High-voltage equipment specification' and '041 Scope for relay protection and system automation'.
Confirmation of absence of mandatory exclusion grounds (convictions, tax debts, sanctions).
Submission of CVs for key personnel meeting competence requirements for design.
Submission of a financing schedule detailing estimated project expenditures for 2026-2028.
Offer drafted in Estonian (with translations for non-English technical documents).
Total bid price in euros excluding VAT.
Nøgledifferentiatorer
Demonstrable cost-efficiency through innovative construction methods or optimized material sourcing.
Exceptional project management and risk mitigation strategies that assure Elering AS of a smooth, predictable project execution.
A highly experienced and competent technical team with a proven track record in similar 110 kV substation projects.
Muligheder for social værdi
While not explicitly required, a commitment to local employment and skills development within the Pärna region can be a subtle differentiator, even if not formally evaluated. This could include a statement on prioritizing local workforce where feasible.
Fokusområder for tilbud
Total bid price in euros excluding VAT100.0%

Achieve the lowest possible price by optimizing all cost components, including direct labor, materials, equipment, logistics, and overheads. Ensure all costs are meticulously calculated and presented clearly in the price table. Avoid any ambiguity that could lead to claims for additional costs later.

Anbefalinger6
Expedite Confidentiality Agreement Process
KritiskLav indsats

Immediately sign and submit the confidentiality agreement to gain access to the technical documentation. This is the first step to understanding the full scope and developing a competitive technical and cost proposal.

Enables timely bid development and avoids delays.
Aggressively Optimize Pricing
KritiskHøj indsats

Given the 100% price weighting, conduct a granular cost breakdown. Explore all opportunities for cost savings through efficient procurement, logistics, and construction methods. Benchmark against similar projects to ensure competitiveness.

Maximizes score for the sole evaluation criterion.
Meticulous Compliance with Mandatory Requirements
KritiskMedium indsats

Develop a comprehensive checklist for all mandatory requirements, including exclusion grounds, eligibility, and technical questionnaires. Ensure all documentation is accurate, complete, and submitted in the correct format and language.

Prevents disqualification and ensures the bid is considered.
Highlight Proven Project Management & Execution
MediumMedium indsats

While price is paramount, subtly emphasize the bidder's ability to deliver complex projects on time and within budget through strong project management, experienced personnel, and robust quality assurance processes. This builds confidence in the bidder's ability to execute the winning bid.

Builds trust and reduces perceived risk for the client.
Thorough Subcontractor Vetting
HøjMedium indsats

Implement a rigorous process for vetting all subcontractors, ensuring they meet Elering AS's requirements regarding corruption and financing of terrorism. Obtain all necessary confirmations and evidence well in advance.

Avoids exclusion grounds related to subcontractors and ensures project integrity.
Ensure Accurate Financing Schedule
HøjMedium indsats

Develop a realistic and detailed financing schedule for 2026-2028, aligning with project expenditures. This demonstrates financial stability and planning capability.

Meets a critical financial requirement and demonstrates capability.
Konkurrencemæssig positionering
Position the bid as the most cost-effective solution without compromising on technical integrity or compliance. Emphasize efficiency and a lean operational model that translates to savings for Elering AS. Highlight a track record of successful, on-time, and on-budget project delivery to reassure the client of execution capability.

Konkurrenter

Opgrader for at se, hvilke virksomheder der sandsynligvis vil afgive tilbud på dette udbud, baseret på historiske indkøbsdata.

Log ind

Krav og kvalifikationer

16 krav på tværs af 5 kategorier

Indsendelse (8)
Obligatorisk (2)
Overholdelse (2)
Teknisk (2)
Finansiel (2)
SUBMISSION REQUIREMENTS8
--The offer must be drawn up in Estonian, except for technical documents, which may be submitted in either Estonian or English. Estonian translations must be attached to documents in foreign languages (other than English technical documents).
--The total cost of the offer in euros without taxes will be evaluated, where the lowest price will receive the maximum score.
--The tender documents contain instructions for bidders, explaining the general data of the procurement procedure, requirements for submitting the offer cost, and grounds for rejecting offers.
MANDATORY EXCLUSION GROUNDS2
--Bidders must provide evidence that they do not fall under grounds for exclusion from the procurement procedure, including confirmations of the absence of convictions, tax debts, and sanctions.
--The contracting authority will check the background of subcontractors in relation to corruption and financing of terrorism, requiring corresponding confirmations and evidence.
ELIGIBILITY REQUIREMENTS2
--Bidders must confirm compliance with the terms of the tender documents, conformity of equipment, and possession of necessary rights, providing powers of attorney if necessary.
--Bidders must submit CVs of key personnel who meet the competence requirements for secondary and primary part design.
TECHNICAL CAPABILITY REQUIREMENTS2
--Bidders must submit the completed questionnaire "031A High-voltage equipment specification" as a mandatory part of the offer to describe the technical parameters of primary equipment.
--Bidders must submit the completed questionnaire "041 Scope for relay protection and system automation" which details the requirements for relay protection and system automation for the 110 kV substation construction works.
FINANCIAL REQUIREMENTS2
--Bidders must submit a financing schedule detailing the estimated project expenditures for the years 2026-2028.
--Bidders must submit a completed price table containing all costs excluding VAT, with fixed prices and transport costs.

Forhåndsvisning af Krav

Tilmeld dig for at se komplette krav og analyser

Dokumenter

19 dokumenter tilgængelige med AI-resuméer

Alltöövõtjate kontrollimise tingimused lepingu täitmise etapisPDF
306637_alltoovotjate_kontrollimise_tingimused... -- 39.4 KB

The contracting authority verifies subcontractor backgrounds regarding corruption and terrorism financing, requiring relevant confirmations and evidence.

Vis
VastavustingimusedPDF
306637_vastavustingimused.pdf -- 14.1 KB

Bidders must confirm compliance with tender document conditions, equipment conformity, and possession of necessary rights, submitting power of attorney if required.

Vis
Palun esitage täidetud küsimustik "031A Kõrgepingeseadmete spetsifikatsioon".DOC
031A Kõrgepingeseadmete spetsifikatsioon_Pärn... -- 51.9 KB

Bidders must submit a completed questionnaire "031A High-Voltage Equipment Specification", which is a mandatory part of the tender for describing the technical parameters of primary equipment.

Vis
Palun esitage täidetud küsimustik "041 Scope for relay protection and system aut...DOC
041 Scope for relay protection and system aut... -- 80.0 KB

Bidders must submit a completed questionnaire "041 Scope for relay protection and system automation" detailing the requirements for relay protection and system automation for the 110 kV substation construction.

Vis
Finantseerimise graafikXLS
Finantseerimise graafik.xlsx -- 19.6 KB

Bidders must submit a financing schedule detailing the projected project expenditures for the years 2026-2028.

Vis
HinnatabelXLS
Hinnatabelid pakkujatele- Alajaam 31012023.xl... -- 59.7 KB

Bidders must submit a completed price table including all costs excluding VAT, with fixed prices and including transportation costs.

Vis
Meeskonna CVDOC
Meeskonna CV.docx -- 34.3 KB

The bidder must submit CVs of key personnel who meet the competence requirements for secondary and primary part design.

Vis
Hindamiskriteeriumid ja hinnatavad näitajadPDF
306637_hindamiskriteeriumid.pdf -- 4.7 KB

In the tender for the construction of Pärna 110 kV substation, the total bid price in euros excluding taxes will be evaluated, with the lowest price receiving the maximum score.

Vis
Kõrvaldamise alused ja kvalifitseerimistingimusedPDF
306637_korvaldamise_alused_ja_kvalifitseerimi... -- 12.0 KB

Bidders must provide evidence that they do not fall under exclusion grounds, including confirmations of absence of criminal records, tax debts, and sanctions.

Vis
Geoloogia, geodeesiaZIP
Geoloogia, geodeesia.zip -- 1.5 MB

Intet resumé tilgængeligt for dette dokument.

Vis
Hankelepingu kavand (Töövõtuleping)DOC
Hankelepingu kavand (Töövõtuleping).docx -- 76.8 KB

This draft works contract outlines the terms for the construction of the Pärna 110 kV substation, including design, material procurement, installation, and commissioning, and specifies the payment procedure.

Vis
Hanke mahtZIP
Hanke maht.zip -- 1.1 MB

Intet resumé tilgængeligt for dette dokument.

Vis
Juhised pakkujateleDOC
Juhised pakkujatele.docx -- 44.4 KB

This document provides instructions for bidders, clarifying general tender procedure information, bid cost submission requirements, and grounds for bid rejection.

Vis
Konfidentsiaalsusleping hanke alusdokumentidega tutvumiseksDOC
Konfidentsiaalsusleping hanke alusdokumentide... -- 48.6 KB

This confidentiality agreement governs the exchange and processing of confidential information within the tender documents between Elering AS and potential bidders.

Vis
Konfidentsiaalsusleping (sõlmitakse eduka pakkujaga töövõtulepingu sõlmimisel)DOC
Konfidentsiaalsusleping (sõlmitakse eduka pak... -- 48.8 KB

This confidentiality agreement governs the secrecy of information exchanged during the tender process and is concluded with the successful bidder.

Vis
KüsimustikudDOC
Küsimustikud_Pärna.doc -- 94.5 KB

This questionnaire is part of the Pärna 110 kV substation construction tender, containing essential information for bid submission.

Vis
NäidisvormidZIP
Näidisvormid.zip -- 147.3 KB

Intet resumé tilgængeligt for dette dokument.

Vis
Skeemid, plaanidZIP
Skeemid, plaanid.zip -- 3.3 MB

Intet resumé tilgængeligt for dette dokument.

Vis
Tehnilised nõudedZIP
Tehnilised nõuded.zip -- 55.8 MB

Intet resumé tilgængeligt for dette dokument.

Vis

Forhåndsvisning af Dokumenter

Tilmeld dig for at se dokumentresuméer og analyser

75
God

Udbudskvalitetsscore

This tender for the construction of the Pärna 110 kV substation is generally well-structured with clear requirements and a reasonable process. However, access to crucial technical documentation is restricted, requiring a confidentiality agreement, which slightly impacts fairness and completeness.

Scoreopdeling

Overholdelse af lovgivning75/100

The tender adheres to standard procurement procedures, including proper CPV codes and a clear timeline. There are no immediate indications of disputes or regulatory non-compliance. Deadlines appear reasonable for the scope of the tender.

Klarhed80/100

The description of the project is clear, and the requirements are generally well-documented. Evaluation criteria are specified, although the weighting is not detailed. Conditions for accessing confidential documents are outlined.

Fuldstændighed70/100

Most basic information is present, including estimated value, duration, and deadlines. However, the dependency on signing a confidentiality agreement to access technical documentation means that not all essential information is immediately available to all potential bidders, impacting completeness.

•Access to essential technical documentation is conditional on signing a confidentiality agreement.
Retfærdighed85/100

The tender is conducted via e-procurement, and the estimated value is disclosed. Objective criteria are stated, and deadlines are reasonable. The requirement to sign a confidentiality agreement before accessing technical documents, while understandable for sensitive information, could be perceived as a minor barrier to full and immediate access for all parties.

•Access to technical documentation requires signing a confidentiality agreement.
Praktisk anvendelighed65/100

E-submission and e-procurement are utilized. The financing condition is detailed in the draft contract. The contract start date is noted as indicative due to technical reasons, which is a practical consideration. However, the dependency on the confidentiality agreement for document access adds a step to the practical submission process.

•Access to technical documentation requires a prior confidentiality agreement.
Datakonsistens90/100

Key fields such as title, reference, organization, and deadlines are populated. There are no reported suspensions or disputes. Dates are logically presented, with reveal, submission, and opening dates clearly defined.

Bæredygtighed50/100

The tender does not explicitly mention green procurement, social aspects, or innovation. It is not indicated as EU funded. This suggests a lack of focus on sustainability criteria.

•No explicit mention of green procurement, social aspects, or innovation.

Styrker

Clear project description and objectives
Use of e-procurement and electronic submission
Well-defined financial and timeline information
Objective evaluation criteria (price-based)

Bekymringer

Restricted access to technical documentation requiring a confidentiality agreement
Lack of explicit sustainability criteria (green, social, innovation)
Indicative contract start date

Anbefalinger

1. Consider providing a summary of key technical aspects accessible without a confidentiality agreement.
2. Incorporate explicit sustainability criteria into future tenders.

Forhåndsvisning af AI-scoring

Tilmeld dig for at se komplette krav og analyser

Komplet analyse af kvalitetsscore
Detaljeret opdeling af underscores
Indsigter i styrker og bekymringer
Strategiske anbefalinger

Intet kreditkort krævet • Opsætning på 2 minutter